Project for the occupation of the Railroad Patio of Pari (first
draft).
I. Basic conditions for the project execution:
a.) The indicated area will have to be empty, except for at least 25 wagons
or more, if possible. All those that remain must be integrated in the project
and, those that cannot, will have to be removed to another place;
b.) Locomotive that should move and distribute the wagons in the indicated
positions by the project;
c.) Assistance to the project execution.
II. Basic project elements:
a. All the wagons will be lined up in the two tracks that arrive just in front
of the main entrance, divided half in each track and the ones that remain lined
up in the track resulting of the match;
b. They will be supported only in the back wheels, raised by derrick and fixed
in this position by steel cables in the tracks;
c. In the wagons raised part, will be fixed plastic white screens (of the type
that protect buildings façades during construction), precisely anchored
so that they stay in constant movement, eventually insufflating by industrial
fans, if necessary.
José Resende
|